Skip to main content
GbR Kadettenweg
All projects

Single-family & apartment buildings

GbR Kadettenweg

Heating system replacement with fuel conversion and decentralised electricity generation for an apartment building.

Project overview

The existing oil heating system in the Berlin-Steglitz apartment building had served for decades, but reached the end of its life in 2014. Residents turned to KRAFTLAND for support with the urgently needed replacement. Converting from oil to gas, combined with the option of generating electricity locally for the building’s residents, was the logical choice.

Design:

  • Complete renewal of the heating system and electrical connection to meet technical connection requirements
  • Funding advice for the planned measures and application for IBB financing
  • Additional funding application through the KfW energy refurbishment programme
  • Design for conversion from oil to gas
  • Hydraulic integration concept
  • Buffer tank sizing
  • Flue system design

Project:

  • Dismantling and proper disposal of the old system, including the oil tank
  • Installation of a CHP unit with 6 kW electrical output and a 45 kW peak-load boiler
  • Additional integration of a domestic hot water heating unit
  • Hydraulic balancing

Services:

  • Certified CHP commissioning
  • Handling all registration formalities
  • Coordination of all project disciplines
  • Initial application for energy tax reimbursement

Get in touch

Your project starts with a conversation.

Briefly describe your project. We will get back to you personally.

+49 30 417 24 488 info@kraftland.de

We use your details to respond to your enquiry. For more information, please see our Privacy Policy.