PUK Group GmbH & Co. KG
Concept and installation of a new energy generation centre for a Berlin production site.
Project overview
PUK Group GmbH & Co. KG is a long-established, independent private Berlin company. A leading manufacturer of cable support systems in Germany and Europe, it is known worldwide. Kraftland GmbH led the concept and installation of PUK Group’s new energy generation centre.
Design:
- Objectives: combine sustainable energy supply and environmentally conscious production with high efficiency and cost-effectiveness
- Analysis and assessment of actual heat demand scenarios
- Determining load behaviour
- Conversion of the energy supply fuel from oil to gas
- Development of a boiler replacement concept
- Design of hydraulic integration for the new generation plant
- Development of an emergency power concept
- Design of a metering and control concept for one or more CHP units and the distribution network connecting all consumer substations
- Coordination of BAFA funding applications
- Assessment of the gas connection
- Assessment of integrating adsorption chillers for production machinery cooling in a second expansion phase
Project:
- Viessmann CHP unit (Vitobloc 200 EM) with 238 kW electrical output provides the heating base load during the heating season and domestic hot water
- CHP unit also used as a standby emergency power supply
- Vitorond peak-load boiler with 950 kW output covers peak heat demand during the heating season
- Plant designed for future expansion
Service
- Coordination of extensive application and registration processes required by the unit’s output class
- Operational management support, such as the initial energy tax reimbursement application and monitoring operating behaviour during start-up
- Application for connection to the low-voltage grid