Public infrastructure
Elbe-Parey
Güsen school campus heat network
Design, tendering and delivery of a CHP-based local heat network for a municipal school campus within eight months.
Services & project data
Scope of services
- CHP and local heat network design
- Financial viability analysis
- On-site electricity use concept for the sports hall
- Funding, registration and project management
Project data
- Supply
- School, nursery and sports hall
- System
- CHP-based local heat network
- Design period
- 8 months
- Commissioning
- 01.01.2018
Starting point
After termination of an expensive heat supply contract, a new supply for the school, nursery and sports hall had to be designed, tendered and installed within eight months.
Design services
Kraftland designed the CHP-based local heat network in HOAI service phases 1–8, prepared the financial viability analysis, designed on-site electricity use for the sports hall and supported funding and grid operator registrations.
Outcome
The plant was commissioned on schedule on 1 January 2018 and supplies heat to the entire campus; the sports hall also uses the electricity generated.